GVHS Logo

Up the Gatineau! Article

This article was first published in Up the Gatineau! Volume 21.

The Great Hydro-Electric Works on the Gatineau River: Some Views From Contemporary Engineering Journals.

Jacques Lecours

Natural Resources and Industry in Quebec

The history of hydro-electricity in Canada is closely linked to the history of its natural resource industries, and nowhere has this been clearer than in Quebec's pulp and paper industry.

The province's largest mills developed in the Canadian Shield and Appalachians where direct access to spruce forests and hydro-electric power was available. Here, American capital was central in the development of pulp-and-paper towns along the Ottawa, Saint Maurice and Saguenay Rivers. Like other pulpwood producing provinces, Quebec was concerned about the export of pulpwood and moved to Jorce the manufacture of newsprint in the province. It did this with differential crown land fees and in 1910 it followed Ontario’s lead in Jforbidding the export of pulpwood. By the First World War, Canada was the world’'s largest producer of newsprint, with 86.4 percent destined for American markets. Despite a drop during the Depression, pulp-and-paper held its position as the largest Canadian export, representing 24 percent of the country's exports in 1954.1

In these conditions, the Gatineau, land of local lumber barons2 since Philemon Wright's first enterprise at the beginning of the 19th century, became the grounds of large American pulp-and-paper interests.

The Gatineau Power Company

The particular circumstance which led to power development on the Gatineau River was the sudden bankruptcy of the Riordon Pulp and Paper Company, a Montreal concern which had recently bought the Gilmour and Hughson holdings in the Gatineau. It also owned valuable water rights on the Gatineau River.

...a new buyer tumed up and the deal finally settled on Feb. 1, 1921. The new owner, a subsidiary of the Canadian International Paper Co. called the Gatineau Co. Ltd., paid $3,016,777. Thus passed the old Gilmour Gatineau empire into the hands of a paper manufacturing company.

Farmer’'s Rapids, where melancholy remains of William Farmer's and Alonzo Wright's unfortunately timed enterprises had slowly rotted Farmer’'s Rapids, where melancholy remains of William Farmer's and Alonzo Wright's unfortunately timed enterprises had slowly rotted away, and the Chelsea Falls, where the Gilmour mills and community buildings still stood, were immensely changed beginning in 1926.3

The force behind these changes was the International Paper Company, then the world’s largest paper producer, which had established Canadian International Paper (CIP) in 1919. In 1922 it had built a plant in Trois- Riviéres which produced 350 tons of newsprint per day; expansion in 1925 increased capacity to 700 tons, making this plant the largest in the world at the time. CIP also built a plant at Kipawa, Quebec (Temiscaming) as well as installations at Grand Falls, New Brunswick.

The Gatineau Power Company was created to construct hydro-electric plants on three sites on the lower Gatineau: a 35 meter drop at Paugan Falls, a 30 meter drop at Chelsea Falls and an 18 meter drop at Farmer’s Rapids. The Quebec Streams Commission was in charge of the creation of a reservoir at Bitobee, 120 miles upstream from the river’s mouth, essential for regulating its flow throughout the year. To create the Baskatong reservoir, it built the Mercier storage dam, as well as two other concrete structures and seven earth-fill dams.

The Gatineau River project was certain to be successful from the outset, since half the initial production from Chelsea and Farmer’s (173 megawatts) was for sale to Ontario Hydro at 25 cycles.4 The other half was destined for CIP’s new plant at Templeton (now Gatineau) which was initially capable of producing 500 tons of newsprint per day, half its ultimate capacity. It was planned that all excess power would be used to produce steam at that plant until it could be absorbed by local demand. All of Paugan’s output, 116 megawatts at 25 cycles, was for purchase by Ontario Hydro.5

Hydro-Electric Works on the Gatineau River
Chelsea, mid-October 1926. View Photo: Archives Hyrdo-Québec

To utilize the power purchased from the Gatineau Power Company, it was necessary to construct a 220,000 volt — later 230,000 volt — transmission line from Paugan Falls on the Gatineau River, 230 miles to a great new transformer station to be built at Leaside [then] on the eastern outskirts of Toronto. Both undertakings imposed novel pioneering demands on Ontario Hydro's engineers. The transmission line carried a higher voltage and was longer than any yet projected in Canada, and the Leaside station required a greater step-down of voltage than was contemplated anywhere.6

In the three years following its establishment, Gatineau Power bought out La Compagnie électrique de Papineauville, the Ottawa-Montreal Power Corporation (from Power Corporation), the Ottawa and Hull Power and Manufacturing Co. and the Ottawa River Power Co. (from Nesbitt, Thompson). Its total installed capacity grew to 407 megawatts in 1930. Throughout its existence, although it acquired many other sites on rivers to the north of the Ottawa and the St. Lawrence which had the potential for development, it built only one plant other than the Gatineau projects, a small (1.7 megawatt) hydro-electric installation at Rawdon on the Ouareau River which was put on line in 1928. It continued to operate twelve of the seventeen small and medium-sized plants it had purchased, including two at the Chaudiére Falls in Hull, the Kipawa plant and one at Bryson. It decommissioned five plants prior to 1930, including one at the Deschénes Rapids on the Ottawa. Another in St. Jérome was closed in 1952.7

Throughout its history, the three large plants on the Gatineau accounted for 85% of the Gatineau Power Company’s installed capacity.

The Plants on the Gatineau

Today, these plants stand as testimony to human ingenuity incarnate in the engineering profession. But they also bear witness to heroic labour, harsh working conditions and environmental upheaval. We must not forget that they were the meeting place of two eras and two cultures: the traditional and the technological.

The engineering journals of the day provide interesting insights into the scope of the great works on the Gatineau. Indeed the developments on the Gatineau were perceived as a major enterprise and were described in many of these journals. In the years 1926-1928, The Engineer, Engineering News Record, The Engineering Journal, The Canadian Engineer, Contract Record and Engineering Review, Power House, The Electrical News, and Electrical News and Engineering all carried extensive coverage of the Gatineau projects.

The damming of the rapids at Chelsea and Farmer's created a reservoir 700 square kilometres in area, reaching up to Paugan's tailrace 20 kilometres upstream and partially flooding 150 farms. An engineering journal of the time describes the change in scenery thus:

Taken as a whole, the river is turbulent, and, as it winds through very hilly and rough country, it has scenic qualities hard to surpass, even in Canada. In fact, the fame of Gatineau scenery has spread far and wide, and the district has become a recognized summer resort...

Naturally, scenic effects and power projects are not synonymous in the popular mind, and there has been, as a perfectly natural consequence, some romantic moaning against possible damage to nature’s handiwork by the hand of man; but of this, more...

The area around Chelsea used to be quite a famous summer resort, and a great number of summer houses will be covered by the new lake. Old haunts, bathing pools. and fishing spots will be no more. The country will take on a new aspect, and, as already stated, there are quite a few people who mourn the passing of the old order. After all, it is quite natutrhaat lth e hundreds who had spent happy days in, and around, this beauty spot, should feel a wrench at the passing of the old aspect;: but, though they are losing something of sentimental value, they are gaining immeasurably. In the future there will be a lake where there was only rough water before. It will be a lake suitable for boating and sailing — something that was foreign to the turbulent Gatineau in the old days. From a purely aesthetic viewpoint it is probable that the scenery will be improved by the additofi a olnake , and so, really, therei s notto hthe ilamnent gof the ‘old timers’, and after all, there seldom is.

What is probably far more to the point than the submersion of a piece of river scenery, in the eyes of certain practical gentlemen, is the fact that the creation of this lake has necessitated the moving back of the C.P.R. for five miles, and the rebuilding of five miles of provincial highway. Items of expense which, naturally, have to be borne by the Gatineau Power Co.8

Hydro-Electric Works on the Gatineau River
Arial view of construction site showing Farmer’s Dam, cottages and workers’ lodgings in the foreground; the Chelsea site can be seen in the background. Photo: Archives Hydro-Québec

These days, one cannot refrain from musing about the effectiveness of such an environmental impact statement.

The total cost of the Gatineau projects was more than $50,000,000. It was therefore imperative that the work proceed rapidly and that the plants be put on line in as short a time as possible. Upwards of 6,000 men were employed at a time during the peak period of the project. Preliminary work at Chelsea was undertaken in October 1925; the plant began production in March 1927, only 17 months later. Farmer’s also took only 15 months to build, from February 1926 to May 1927. At Paugan, concrete was first poured on the 25th of May 1927, and the first generating unit was put on line on May 14th 1928. By the following October, a total of six units had been installed at Paugan with two more in 1931 and 1954.

Construction Work

The engineering journals naturally concentrate on technical descriptions of the dams and plants being built and on the work programs. Occasionally, however, they afford interesting points of view on how the work was actually managed and carried out. The following excerpts are taken from a 1926 address to the Rotary Club in Ottawa by the chief engineer of the Chelsea and Farmer's projects. The presentation gives a general overview of the Gatineau projects but it also deals with some less technical considerations.

A dam will be built across the river at the site of the old Gilmour and Hughson Mill at Chelsea Island. The upper part of the island will be incorporated into the dam, the top of which is to be just level with its highest point. The power house, which forms a part of the dam, will block the west channel. The latter enlarged and deepened will serve as the tail-race....

It is probable that at least 4,000 men will be employed on the construction work particularly covered by this address9 and perhaps 1,500 or 2,000 more on the other works10, forming a part of this enterprise. There are also a considerable number of teams11 required.

As far as is practicable, it is the policy to give employment to local people. It must, however, be recognized that much of this work is of a special nature, as, for instance, work with explosives, [and] the work in and around water, and it is dangeras owuells as impracticableto use men unfamiliar with its nature.

Another difficulty arises with people not used to this class of work, and especially with farmers. They do not seem to realize that it is necessary that they work steadily. Many are anxious for work. They will start in and work for a few days, then stay away to go to market or to do a little work arotuheinr dfar m. When they report back and find their places filled, they think they have a genuine grievance and are being discriminated against. It may be thought that with such a large force the absenof ca efe w will not make much difference, but this is not so, for every man's duties fit in with those of many others, and if in most caa splaece scann ot be filfolr ea dday , serious delay results.

A very good example of this occurred at Chelsea. Farmers' teams were being employed to haul sand from the pit to a hopper for supplying the mixers. The distance was short and four teams were just sufficient for the purpose. At this time about 100 cubic yards of concrete were being placed per day by this outfit at a total cost of $1,000.

If one team stayed away for a day and could not be replaced, as it generally could not, the entire output was cut down 25 percent, without much decreasing the cost. Accordingly, the absence of one team for a day would cause a loss of nearly $250. The farmers’ teams were so irregular that it became necessary to replace them by teamns hired from a man who used them for this purpose only. This is an extreme case of course, and local labour is used whenever practicable.12

Construction Camps

The engineer then gave some detailed information as to how the construction camps, the sudden cities of bunkhouses and mess-halls, actually operated.

All employees are free to live outside the camps of the company. In fact, it is to the company’s interests that they do so, as the charge made for board, while it is a little more than pays for the food, does not, on jobs of this character where the camps are used for a year at most, cover the cost of the camps themselves and of their equipment. It has been difficult to estimate the camp accommodations required, as in a settled community like this, it is hard to judge how many men will prefer to live outside the camps. Up to the present, sleeping accommodations, including married quarters, have been supplied about as follows:

Chelsea...........1,200
Farmer's..........1,000
Gatineau.........1,500

The dining room accommodations are somewhat larger than this.

At each site a number of houses of varying grade have been constructed for the married superintendents, engineers, general foremen, etc. Also at each point a staff house has been constructed for the unmarried members of the staff or for those who do not care to bring their families on the job.

Waitresses are employed for serving in the dining rooms, and dormitories similar to the staff houses are provided for their accommodation. They are in [the] charge of a matron at each camp. It is found that by their superior neatness, girls give much better satisfaction than the class of men waiters that can be secured for this work.

Hydro-Electric Works on the Gatineau River
Typical bunk house for 64 men. Taken at Farmer's dam site, 8 February 1926. Photo: Archives Hydro-Québec

The men's bunk houses are supplied with metal bedsteads, mattresses and blankets. A building used exclusively for a bath house and toilet is provided for each 350 men. There is a constant supply of hot and cold water, and they are equipped with ample shower baths and toilet facilities.

We are preparing to feed at least 4,000 people throughout the summer, and the following is a list of some of the principal items of supply required for a month:

Beef, 90,800 Ibs.; pork, 32,000 lbs.; fish, 11,000 lbs.; butter, 12,000 lbs.; eggs, 9,700 doz.; milk, 6,200 gals.; potatoes, 1,800 bags: flour, 650 bags; sugar, 42,300 lbs.; tea and coffee, 7,000 lbs.; canned goods, 136,000 Ibs.; or a total of about 280 tons.

About 260 employees in all are requirefdor the purpose of taking care of the camps and dining rooms.13

Another interesting insight into the construction camps is given by this simpler view of things at Paugan:

All men are housed and fed on the job, the usual care in sanitary details, which is characteristic of the contracting engineers, being observed. Comfortable staff houses are provided for the executive staff, and stores, barber shops, etc. are maintained within the works.

All men in the camp are provided with medical attention, and a very rigid discipline is enforced, a special body of police being maintained to preserve order and to see that all camp regulations are carried out.14

Hydro-Electric Works on the Gatineau River
Excavation work at the power house site, Farmer's, 29 May 1926. Rock is broken by pneumatic drills and loaded by hand into large wooden boxes which are hoisted onto trains. Material is brought to a crushing plant for use in concrete. Photo: Archives Hydro-Québec

There seem to be no visible remains of the construction camps that once stood on the left bank of the river just upstream from the Farmer's plant, on Chelsea Island and on the right bank at Paugan because the bunkhouses, mess halls and other buildings were not set on permanent foundations. Some engineers’ and superintendents’ cottages remained for a number of years to house plant operators, but they were eventually torn down because they were no longer used. Some of their foundations are still visible upon superficial inspection. Further investigation with site plans and photographs in hand would perhaps allow one to discover some vestiges of mixing plants as well as remains of the railway systems for the sites.

Managing a Significant Heritage

The hydroelectric plants of the Gatineau are an important part of Quebec's industrial heritage, and Hydro-Québec recognizes their significance.15

Chelsea, Farmer's and Paugan are now more than 65 years old. They have always performed well but, given their age, they must be refurbished in order to prolong their usefulness for the decades to come. Hydro-Québec has therefore initiated a large modernization program for these and many other plants of the same era, notably those on the lower St. Maurice (another fascinating chapter of Quebec’s industrial history). Modernization does not mean disregard for the heritage value of these monuments of industry. As it should be, Hydro-Québec’s main objective is to provide the best service: production of electricity must be safe, reliable and environmentally sound. As well, the cultural heritage is part of the environment and therefore must be taken into consideration. Detailed surveys of heritage structures allow for their management in a respectful way.

Hydro-Electric Works on the Gatineau River
Paugan, 12 November 1927, Partial view of camp. Trestle in the middle carries railway from material stockpile to actual construction site. Photo: Archives Hydro-Québec

The industrial heritage is often seen as a an offspring of the history of technology. While this is indeed one of the major reasons for heritage preservation, we must not forget the thousands of men and women who actually built these great monuments. The human dimension of the industrial heritage is of the greatest interest: after all, these resources are significant because they are human creations.

Information such as has been presented here is therefore extremely valuable. Knowledge of historic industrial properties rests on numerous and varied sources: professional journals, construction photographs, manufacturers’' catalogues, company promotional materials, original plans and specifications, Hydro-Québec's archives are a repository of such material. In a related vein, its developing oral history program will bring life to archival materials and field surveys.

Footnotes

  1. Brian Young and John A. Dickinson A Short History of Quebec: A Socio-Economic Perspective (Toronto, Copp, Clark, Pitman Ltd., 1988), pp. 187, 188.
  2. That era has been well documented in: John W. Hughson and Courtney C. J. Bond Hurling Down the Pine (Chelsea, The Historical Society of the Gatineau, 1964, Third Edition 1987).
  3. John W. Hughson and Courtney C. J. Bond, op. cit., p. 59.
  4. Alternating current had been standardized to 60 cycles per second throughout most of America by the first decades of the century. However, some areas continued to be served at 25 cycles for a number of years, relying on relatively obsolete technology. Conversion was a considerable enterprise, involving amongst other things the replacement of all appliance motors. Ontario Hydro did not start standardizing its system to 60 cycles before 1949.
  5. This contract caused much difficulty for the Gatineau Power Co. in the years following 1935 when Ontario Hydro unilaterally cancelled it because the demand for power, following the recession, was much less than had been projected. Beauharnois Power, also a large exporter to Ontario, found itself in a similar situation. See T.D. Regehr The Beauharnois Scandal, (Toronto, Buffalo, London, University of London Press, 1990).
  6. Merrill Denison, The People's Power — the History of Ontario Hydro, (Toronto, McClelland and Stewart Limited, 1960), p. 177.
  7. Hydro-Québec Direction Architecture, service Etudes préliminaires, Inventaire du patrimoine technologique et architectural d'Hydro-Québec — région Laurentides (avril 1988).
  8. R.C. Rowe, “Developing 400,000 H.P. for the World's Largest Paper Maker,” Power House, Vol. 20, No. 21 (November 1926).
  9. These are the Chelsea and Farmer's Rapids power plants and the paper Mill at Templeton (Gatineau).
  10. Paugan and the dams impounding the Baskatong reservoir.
  11. What is meant is teams of horses. It is interesting to note that hand labour, horsepower, steam engines, internal combustion engines and electricity were all used simultaneously on these construction sites.
  12. *4000 Men Will Be Engaged on Gatineau River Power Projects”, Contract Record and Engineering Review (June 1926), pp. 547-551.
  13. ibid., pp. 547-551.
  14. R.C. Rowe, “Hydro Development at Paugan Falls,” The Canadian Engineer, Vol. 54, No. 8, (Feb. 1928).
  15. Hydro-Queébec, Vice-présidence Environnement, Inventaire du patrimoine bati et technologique d'Hydro-Québec — Evaluation comparative des installations hydroélectriques (octobre 1994).

Volume 21 table of content.

Return to List of articles